"With that information in mind, $200 million over, 2 years behind schedule, what is different now to ensure that the Cannon renewal project, which is already $752.7 million, is going to stay within bud..."
"So with that significant change, it would seem it would be--because you are changing a major project midstream, effective auditing and oversight seems to be it would be more important then."
"The problem is it's our interpretation of that science to meet political ends, which has been happening since the dawn of man."
"I am surprised to see that our printing revenue is increasing in that area, because, as Congressman Raskin asked, you know, do you think that printing is dying, and what we see is that this is actuall..."