On the recordSeptember 20, 2013
Regrettably this week, we had to wish TransCanada an unhappy fifth birthday. They've now been waiting for 5 years since first applying for the permit for the construction of the Keystone pipeline. Even though this anniversary was an unfortunate milestone, what is fortunate is that the southern leg of the Keystone pipeline will be completed by the end of 2013. However, the delay of the northern leg puts 4,000 people on hold for work. Today, the southern leg is on day 410 of construction, and the hardworking Americans who devoted time and effort deserve these jobs. While this administration promotes a job-focused agenda, it continues to cripple our Nation's entrepreneurial spirit. It's time we move past the rhetoric and make sure America continues moving forward. ____________________