What is going to be the timeline for submitting the scope of work recommendations to FEMA to see the transmission and distribution of funds?
I think there are several questions that need to be answered.
Why, if we do have $9.6 billion in Federal funds to get a renewable system, to change the power grid, make it more resilient, and help with ...
Please provide us the latest generation report and the tables/report on the condition of the generating fleet.
What do you answer to those who say we need not rebuild or convert to new fuels any of the existing fleet, but just fix it to keep running u...
Can you please provide us a specific timeline for LUMA submitting project Scope of Work documentation for FEMA/COR3 projects?
Natural gas is a good bridge fuel, and the future is in wind and solar.
Is our system near to a complete collapse here soon?
If you don't have power in some rural communities, they will not have water usage at the same time.
I ask that the EPA review the relevant science and issue a new standard for perchlorate, if necessary.
The diesel fuel oil and coal plants have to go, and that is my message to PREPA and to the Fiscal Board.
Can you identify critical units that absolutely must go offline soon for maintenance?
The generation system of Puerto Rico, as today, is not as reliable as it should be.
You agree with me that some of the transformers and the breakers can be taking 1 or 2 years of manufacturing, correct?
should the Federal Government provide further testing in the instance of private wells when they are located near Superfund sites?
if you fail to study a specific source or route of exposure, could the risk be adequately determined?
Should the EPA have removed regulatory guidelines for contaminants in some wells that people utilize for drinking water?
I hope this hearing provides better guidance to all of us in addressing this issue, in answering what is going to happen when the people of ...